Johnston Road Project Updates
Follow this page for updates on the road projects taking place along Johnston Road.
Bookmark this page to stay updated on the progress of projects along Johnston Road. The current project is the replacement of two failing drainage culvert pipes beneath the roadway at Fort Pierce Farms Water Control District (FPFWCD) Canals 16 and 17. Johnston Road is expected to fully reopen by late August.
Have questions about this page? Email publicworks@stlucieco.gov.
August 7, 2026 Updates:
Sheet pile is loaded onto a truck on August 7.
- The sheet pile has been removed and water is flowing through the culvert at Canal 16;
- Work continues to restore the surface above the culvert pipe;
July 29, 2026 Updates:
Work continues on the box culvert at Canal 16 on July 29.
July 24, 2026 Updates:
All four side pipes have been installed and covered.
- PRP compacting material with plate tamper;
- Densities of compacted material is being tested;
July 23, 2026 Updates:
Work takes place on the Canal 16 box culvert on July 23.
- A trench for the northeast drainage pipe is being excavated;
- Two southern drainage pipes have been installed;
July 20, 2026 Updates:
Workers have made progress with dewatering of the Canal 16 project site.
July 16, 2026 Updates:
Water is seen filling the project site on July 16 following recent rainfall. Progress has been slowed this week due to recent stormy weather.
July 14, 2026 Updates:
- All segments of the concrete box culvert have been installed;
- Dewatering of the project site is underway following recent heavy rainfall;
July 9, 2026 Updates:
One of the final segments of the Canal 16 concrete box culvert is guided into position on July 9.
The water level of Canal 16 is seen against the sheet pile dam on July 9. Recent rainfall and stormwater runoff from surrounding areas impacted some of the culvert installation earlier in the week.
July 6, 2026 Updates:
The Canal 16 concrete box culvert project is seen on July 6. Dewatering of the site continues following recent rainfall.
July 1, 2026 Updates:
Bedding stone is unloaded onto Johnston Road on July 1.
- Well points have been installed and dewatering of the new trench area is under way;
- The contractor is back filling the new boxes on the western half of the project;
- The remaining pipe beneath Johnston Road is being excavated;
- Installation of the remaining boxes is scheduled for next week;
June 30, 2026 Updates:
Pieces of sheet metal used to strengthen the sides of the work site are being removed from the western half of the culvert on June 30.
- PRP Construction continues to remove side sheet piles from the western half of the Canal 16 culvert;
- Following the removal of the sheet piles, PRP will start excavating the roadway section and filling in the 11 installed boxes;
- Once this backfilling and excavation are complete, PRP will begin installing the remaining segments of the box culvert;
June 29, 2026 Updates:
Eleven of 24 segments of the concrete box culvert beneath Johnston Road at Canal 16 are seen on June 29.
- As work progresses on the culvert pipe at Canal 16, the contractor is planning to remove the side sheet piles this afternoon;
- PRP will start excavating the roadway section and filling in the 11 installed boxes;
- Once this backfilling and excavation are complete, PRP will restart installing boxes for the eastern half of the culvert;
June 25, 2026 Updates:
Multiple segments of the concrete box culvert at Canal 16 are seen during installation on the west side of Johnston Road on June 25.
Two segments of the concrete box culvert are seen on June 25 prior to installation.
June 23, 2026 Updates:
Water flows between two man-made sheet metal walls as pumps dewater the Canal 16 culvert site on June 23.
- Dewatering of the work site at Canal 16 is under way;
- Dewatering is expected to take five to seven days to complete. During this time, residents may see little to no additional work taking place, as the ground needs to be dried before the culvert replacement may proceed;
- Chip sealing of Johnston Road north of the Canal 16 project is currently under way. Full depth reclamation of the roadway is taking place this week, with that work expected to continue through Friday, June 26. One lane of traffic remains open during this operation, with flaggers directing motorists;
Full depth reclamation of Johnston Road north of the Canal 16 site is seen in progress on June 23.
June 19, 2026 Updates:
Workers install sheet piles on June 19 to reinforce the sides and effectively "box in" their work area at the Canal 16 site. The sheet piles will help prevent the sides from collapsing into the work area.
The box culvert at Canal 17 has been installed, with the road above it still to be paved.
June 4, 2026 Updates:
Work continues on Johnston Road at the C-16 Canal project site ahead of the arrival of the box culverts.
The C-17 Culvert site is seen on June 4.
May 29, 2026 Updates:
Sheet pile installation takes place on the eastern side of Canal 16 on May 29.
May 28, 2026 Updates:
Workers lay sod along the southwestern bank of Canal 17 on May 28.
Workers construct a roadside drainage swale on May 28.
Sheet piles are seen in place on the western side of the Canal 16 project on May 28.
May 27, 2026 Updates:
Water flows through the concrete box culvert on May 27, 2026.
One of the side drain pipes is visible as work continues on swales parallel to Johnston Road at Canal 17.
Sheet pile installation has begun at the C-16 culvert project site.
- Rubble riprap has been installed along the banks;
- Work is progressing on swales along either side of the road that lead to drainage pipes connecting to the culvert;
- Sheet piles at either end of the C-17 project site have been removed, allowing water to flow through the box culvert;
- Sheet piles are being installed at the C-16 project site;
May 14, 2026 Updates:
Underground drainage pipes are attached to the sides of the box culvert.
May 13, 2026 Updates:
Rubble riprap is placed along the northeastern bank of Canal 17 on May 13, 2026. This material will help stabilize the terrain and prevent erosion.
May 5, 2026 Updates:
The final segment of the box culvert at Canal 17 is set in place on May 5, 2026.
- The full 144-feet long box culvert beneath Johnston Road at Canal 17 is now in place.
- Workers will ensure that joints are sealed and begin backfilling around the box culvert.
May 4, 2026 Updates:
The box culvert continues to take shape, as work continues on the eastern half of the pipe in Canal C-17 on May 4, 2026.
April 30, 2026 Updates:
The eastern side of the project is seen on April 30. With backfilling complete, the next box culverts are scheduled to be delivered next week.
- The last pieces of the 84-inch corrugated metal pipe (CMP) have been removed;
- Bedding stone on the east side of the project has been set in place ahead of the installation of the remaining box culverts;
April 29, 2026 Updates:
Work is under way to build the road back up over the western half of the project. Once complete, installation of the remaining segments of the box culvert will take place on the eastern half.
April 23, 2026 Updates:
Two additional segments of the culvert have been installed, as seen on April 23.
April 22, 2026 Updates:
Multiple concrete boxes are lined up in the C-17 Canal on the west side of Johnston Road, as seen on April 22.
A section of the existing failing culvert pipe is removed on April 22.
- Workers are excavating to reveal and remove portions of the existing culvert pipe that remain beneath the roadway.
- Crane operations to install additional segments of the concrete structure are expected to resume on Thursday, April 23.
- As of Wednesday morning, 10 of the 29 boxes are installed.
April 21, 2026 Updates:
A segment of the concrete box culvert is lowered into the canal as two additional segments arrive on April 21.
- Segments of the concrete box culverts have begun arriving at the project site.
- Six segments were set in place.
- Additional segments are scheduled to be installed on Wednesday.
April 16, 2026 Updates:
A portion of the underground culvert pipe is removed, as seen on April 16.
April 14, 2026 Updates:
PRP Construction lowers a hose into FPFWCD Canal 17 on April 14. Work continues to remove water left over from last week's rain so that normal operations may resume.
- PRP Construction continues to remove water from the project area. Once the water table is lowered and the ground is dry, crews can continue removing the existing pipe and setting the new concrete box in place.
April 10, 2026 Updates:
More than six inches of rain fell over Fort Pierce between April 6 and April 9, per TCPalm reporting.
April 6, 2026 Updates:
A crew excavates to uncover the culvert pipe that crosses beneath Johnston Road at Canal 17 on April 6, 2026.
Mounds of bedding stone have been placed along the road on April 6, 2026.
March 11, 2026 Updates:
- A road closure notice is issued for culvert repairs at FPFWCD Canals 16 and 17, north of Meadowood. Beginning March 30, this section of road will close so that two failing drainage culvert pipes beneath the roadway may be replaced. The road is expected to remain closed for approximately three months while this work is underway.
March 6, 2026 Updates:
- Repairs to culverts at FPFWCD Canals C-16 and C-17 are expected to begin in late March.
- Watch the Board discuss this project during the March 3 Regular Meeting.
February 12, 2026 Updates:
- Johnston Road has reopened.
- See a timeline of the Johnston Road at Canal 1 Emergency Culvert Repair here.